Question
The time required to kill microorganisms at a given lethal
temperature is calledSolution
Thermal death is the death of a population of microorganisms due to exposure to an elevated temperature.
A and B can complete a work together in 36 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed ...
'A' alone can do some work in 10 days, 'B' alone can do the same work in 15 days. If they work on alternate days, starting with 'B', then the work will ...
βMβ and βNβ can do a piece of work in 9 days and 18 days, respectively. βMβ started working alone and was replaced by βNβ after 3 days. ...
βAβ and βBβ can complete a certain work in 15 days and 10 days, respectively. They started working together and worked till completion of the wo...
βAβ can do a piece of work in 15 days. βBβ can do 80% of the same work in 20 days. If they work together for the entire time and get paid Rs.140...
- Suman alone can complete a work in 40 days. Pooja is twice as efficient as Suman. Find the percentage of work completed by Suman and Pooja together in 8 da...
A team of 12 men and 18 women can complete a construction project in 24 days. If 6 women alone can do the same project in 144 days, how many days will 4...
Ravi can complete a task alone in 12 days. After a few days, Mohan joins him and both complete the remaining 50% of the work in 3 days. How long will Mo...
45 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for ...
A can complete a work in 12 days and B can complete the same work in 18 days. They work together for 4 days and then B leaves. In how many more days wil...