Question

    Match List I with List II

    src="https://www.ixambee.com/questionimage/ICAR-JRF-Recruitment/1703662905-ICAR.AIEEA.PYP.2020.eng.85.png" alt="" />   Choose the correct answer from the options given below
    A A-IV; B-III; C-I; D-II Correct Answer Incorrect Answer
    B A IV: B-II; C-III; D-I Correct Answer Incorrect Answer
    C A-B-III; C- IV; D-I Correct Answer Incorrect Answer
    D A-III; B-C-I; D-IV Correct Answer Incorrect Answer

    Solution

    Auger hole method is expressed as 523000 a2 log10(Y0/Y1)/ ∆T  Pipe cavity method is expressed as πr2 ln (Y0/Y1)/(S(t2-t1) Constant head permeameter is expressed as q×L/(A×t× ∆H)   Spacing between drains is calculated by 4K(b2-a2)/q

    Practice Next

    Relevant for Exams: