12 children and 18 men complete an artwork in 9 days. Each child takes twice as long as a man to finish the artwork. How many days will it take for 18 m...
Raman can complete a certain task by himself in 30 days. Both Raman and Rajat worked together to finish this task, earning a combined wage of Rs. 5,850....
A man takes 200 days to finish a work alone. If he started working alone and joined by one more man having same efficiency as of him every day from 2nd ...
Tony has 3 sons – Harry, Peter and Murphy. Harry and Peter can complete the work in 24 days and 36 days respectively. In how many days Murphy will...
33 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for ...
Three workers, A, B, and C, can complete a task in 40 days, 72 days, and 45 days respectively. They start working together, but A leaves 20 days before ...
P and Q together can finish a task in 72 days while Q and R can do it in 48 days. If P worked for 18 days, Q worked for 30 days, and then R finished the...
Ankit and Priya together can complete a piece of work in 200 days and 10 minutes, while Priya and Vikas together can complete the same work in 130 days ...
A and B can complete a work together in 36 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed ...
A can finish a piece of work in 12 days and B can finish it in 18 days. They work together for 3 days and then B leaves. In how many more days will A al...