ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    Question

    Before the work of audit is commenced, the auditor plans

    out the whole of audit work is called _________.
    A Audit plan. Correct Answer Incorrect Answer
    B Audit note. Correct Answer Incorrect Answer
    C Audit risk. Correct Answer Incorrect Answer
    D Audit programme. Correct Answer Incorrect Answer

    Solution

    Before the work of audit is commenced, the auditor plans out the whole audit work in a structured manner, detailing the procedures, scope, and timing of the audit tasks. This planned set of procedures is known as an "audit programme." It serves as a roadmap for conducting the audit efficiently and effectively.