Question
In the following questions two columns are given
containing three sentences/phrases each. In first column, sentences/phrases are A, B and C and in the second column the sentences/phrases are D, E and F. A sentence/phrase from the first column may or may not connect with another sentence/phrase from the second column to make a grammatically and contextually correct sentence. Each question has five options, four of which display the sequence(s) in which the sentences/phrases can be joined to form a grammatically and contextually correct sentence. If none of the options given forms a correct sentence after combination, mark (e), i.e. “None of these” as your answer.Solution
Sentence A - Due to a lack of new features, Can match with a concluding independent clause only as there is a “comma” at the end. D, E and F are dependent clauses. Hence, there is no correct pair. Sentence B - Samsung, the world's biggest seller of smartphones Can match with a dependent clause only adding something more about Samsung. D is incorrect as we say that Samsung is a leader and D talks of “following the leader” and thus is meaningfully incorrect. E will be grammatically incomplete – Samsung, wooing customers for now,_____. (We need another clause to complete). F is incorrect as it refers to Samsung as a “device”. Hence, there is no correct pair. Sentence C - China's Huawei, the world's second biggest smartphone seller, Can match with a dependent clause only adding something more about Huawei. D is correct as we say that Samsung is a leader and D talks of “following the leader” and thus is meaningfully correct. E will be grammatically incomplete – Huawei, wooing customers for now,_____. (We need another clause to complete). F is incorrect as it refers to Huawei as a “device”. Hence, C-D is the correct pair.
A company hires workers A, B, and C to finish a project. A can complete the project in 30 days, B can do it in 24 days, and C can complete it in 20 days...
A can do a piece of work in 15 days, B is 25% more efficient than A, and C is 40% more efficient than B. A and C work together for 3 days and then C lea...
A can complete a piece of work in 10 days. B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many...
Three workers P1, P2 and P3 got work from the contractor. In 30 days, ‘P1’ completed 30% of work. ‘P2’ is 20% less efficient tha...
Ajay and Bheem collectively earned Rs.9,000 for completing a task, with Bheem's share being Rs.3,000. If Bheem can complete the work on his own in 48 da...
. If 3 goats or 5 sheep can graze a field in 56 days, then in how many days can 6 goats and 10 sheep graze the same field?
‘A’ can complete a work in 20 days and is 20% more efficient than ‘B’. ‘A’ and ‘B’ start the work together, but ‘A’ leaves after 10 ...
- C is 37.5% more efficient than A, and A is 60% more efficient than B. If A, B, and C together can complete a task in 40 days, how long will it take A alone...
12 men can finish a work in 20 days by working 6 hours a day. How many more men are needed to finish the work in 12 days by working 6 hours a day?
A and B together can finish a job in 12 days. B alone takes 30 days. How long will A and C together take to finish the same job if C does one-fourth of ...