Question
Which of the following correctly explains the
standardised approach for computing credit risk under Basel capital requirements, in India?Solution
BASEL-III provides two options for measurement of capital charge for credit risk - standardised approach (SA) and Internal rating based approach (IRB). Under the SA, the banks use a risk-weighting schedule for measuring the credit risk of its assets by assigning risk weights based on the rating assigned by the external credit rating agencies. The IRB approach, on the other hand, allows banks to use their own internal ratings of counterparties and exposures, which permit a finer differentiation of risk for various exposures and hence delivers capital requirements that are better aligned to the degree of risks. The IRB approaches are of two types: Foundation IRB and Advanced IRB. In India, banks have been advised to compute capital requirements for credit risk adopting the SA.
P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work &l...
- Person A is twice as efficient as Person B. Person B can complete a certain task in 32 days, while Person C takes 4 days more than Person A to finish the s...
‘A’ can do a piece of work in 15 days. ‘B’ can do 70% of the same work in 20 days. If they work together for the entire time and...
Person A is 80% more efficient than person B. A and B together can complete a certain task in 10 days, while B and C together can complete the same task...
'A' and 'B' can do a piece of work together in 30 days. They worked together for 18 days, and then left the work. The remaining job was finished by 'C' ...
A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 6 days. In how many days can A and B finish t...
Vijay can do a piece of work in 10 days and Sanjay can do the same work in 15 days. If Vijay works for 4 days and got Rs. 1680, and the remaining work w...
- 'Amit', 'Ravi', and 'Neha' can finish a piece of work in 66, 99, and 132 days respectively. They all started the work, but Amit left 8 days before the work...
- Ritu completes 50% of a project in 25 days, while Sheetal completes 40% in 32 days. Ritu works for 30 days and then stops. Find the time Sheetal needs to f...
X can do a piece of work in 22 days. He worked at it for 11 days and then Y finished it in 15 days. In how many days can X and Y together finish the work?