Question
The product and capital market reforms continued slowly
over the decade of the 1990s in India. The introduction of New Telecom Policy was also a milestone event in this regard. When was the New Telecom Policy introduced?Solution
· The macroeconomic imbalances of the late 1980s and early 1990s pushed the government towards introducing the structural reforms of 1991. The high combined deficit of the central and state governments, elevated inflationary pressures, and large and unsustainable current account deficit (CAD) led to a balance of payments crisis in the Indian economy. In response to the situation, trade and investments were liberalised in 1991. · Import licensing on almost all intermediate inputs and capital goods was done away with, and the entry restrictions for firms were simplified. The new policy encouraged the entry of private sector firms by ending the public sector monopoly in many sectors and initiating the automatic approval policy for FDI up to 51 per cent. The exchange rate was made flexible and allowed to depreciate as necessary to maintain competitiveness. The rupee was made fully convertible on the current account and partially on the capital account. These reforms had a positive effect on the economy. · The product and capital market reforms continued slowly over the decade of the 1990s through the introduction of New Telecom Policy 1999. And the government set up a dedicated Ministry to take this agenda forward. It sold equity stakes in some CPSEs and privatised companies such as Maruti Udyog, Hindustan Zinc, Bharat Aluminum, and Videsh Sanchar Nigam Limited.
A and B together can complete a task in 12 days, while B and C together can complete the same task in 15 days. A and C together take 20 days to finish i...
A company hires workers A, B, and C to finish a project. A can complete the project in 30 days, B can do it in 24 days, and C can complete it in 20 days...
‘A’ and ‘B’ can do a piece of work in 10 days and 20 days, respectively. They started working together but ‘A’ left after 3 days. Find the t...
A contractor undertook to make 20 km of roadway in 48 weeks. In 28 weeks, 8 km was completed by 120 men working 12 hours a day. The men then agreed to w...
- Aisha and Neel can complete a job alone in 66 days and 99 days respectively. Working together, they earn a total wage of Rs. 11,550. How much does Aisha re...
A alone can complete 50% of a work in 9 days while B takes 6 days more than A to complete it. If B and C together can complete the work in 12 days, then...
'Aman' and 'Bittu' alone can do some work in 30 days and 45 days, respectively. They work together for eleven days after which both 'Aman' and 'Bittu' a...
A, B and C can mow a field in 36 days, 72 days and 54 days respectively. All the three began the work together on January 1, 2016, but A left 8 days and...
P can complete a piece of work in 15 days. Q in 20 days and R in 30 days. P and R worked together for three days and then P was replaced by Q. In how ma...
- ‘Neha’ can complete a task in 90 days. She worked for 54 days and then left. The rest of the task was completed by ‘Karan’ in 24 days. How much tim...