    Which of the following statements are not correct:

    1.    Project Design and network analysis refers to detailed work plan to the project and its time profile

    2.    There is a prescribed format for the preparation of a project report.

    3.    A project plan is a formal, approved document that is used to manage and control a project.

    4.    The promoter’s capacity and competence should be examined with reference to their management background, traits as entrepreneurs, business or industrial experience

    5.    The Economic Appraisal consists of two parts: measurement of the distribution of the income due to the project and identification of the impact on the basic needs objectives of the society.

    A 1 & 3 Correct Answer Incorrect Answer
    B 2 & 5 Correct Answer Incorrect Answer
    C 2 & 4 Correct Answer Incorrect Answer
    D 4 & 5 Correct Answer Incorrect Answer
    E 1 & 5 Correct Answer Incorrect Answer

    Solution

    There is no prescribed format for the preparation of a project report. Measurement of the distribution of the income due to the project and identification of the impact on the basic needs objectives of the society are parts of Social/distributive Appraisal and not Economic appraisal