· The International Monetary Fund (IMF) has corrected an error in its calculations to now project that India would become a $5-trillion economy by 2026-27. · Earlier the data given by the Fund had shown that this could be achieved by only 2028-29, two years after the Union Finance ministry's latest projections and a four-year delay over the original goal set by the government. · Prime Minister Narendra Modi in 2019 envisioned making India a $5 trillion economy by 2024-25. However, this target was hampered by Covid-induced lockdowns.
Tony has 3 sons – Harry, Peter and Murphy. Harry and Peter can complete the work in 24 days and 36 days respectively. In how many days Murphy will...
A work can be completed by ‘A’ and ‘B’, alone in 10 days and 12 days, respectively. Find the number of days taken by ‘C’ to complete the sam...
A contractor hired 80 workers to complete a work in 60 days. After 40 days, it was found that only half of the work was completed. Find the number of ex...
A painter charges ₹500 for every hour of work. If he works for 6 hours a day and completes a project in 5 days, what is the total amount charged by th...
Aamir is twice as efficient a worker as Bender and together they can complete a work in 42 days. In how many days will Aamir alone complete the same work?
Karan, Arjun and Krunal alone can complete a work in 30, 45 and 36 days respectively. All of them started working together but after 3 days from start K...
18 skilled workers can complete a task in 12 days while 24 semi-skilled workers need 15 days to complete the same task. 12 skilled workers started the t...
Two workers A and B were put to some work. If A worked alone, he would have taken 8 hours more than when both A and B had worked together. If B worked a...
"'Mahesh' is 40% less efficient than 'Neeraj.' 'Neeraj' takes 30 days fewer than 'Mahesh' to finish the same work. Find the time taken by 'Neeraj' to fi...
‘P’, ‘Q’, and ‘R’ can complete a task in 10 days, 15 days, and 20 days, respectively. ‘P’ starts the task alone a...