Question
Which state signed an agreement for the 1,200 - MW Kalai
- II hydroelectric project in the Lohit river basin, and how much is the project estimated to cost?Solution
Explanation : Arunachal Pradesh signed an agreement for the 1,200 - MW Kalai - II hydroelectric project in the Lohit river basin, estimated to cost Rs 13,000 crore .