Consider the following statements:
1. The auctions of the G-Secs are conducted on the electronic platform called the E-Kuber.
2. Only the members of E-Kuber can participate in the primary auction of the G-Secs.
3. G-Secs are issued through auctions conducted by RBI.
Which of the statements given above is/are correct?
Statement 1 is correct: Auctions are conducted on the electronic platform called the E-Kuber, the Core Banking Solution (CBS) platform of RBI. Statement 2 is incorrect: All non-E-Kuber members including non-scheduled UCBs can participate in the primary auction through scheduled commercial banks or PDs (called as Primary Members-PMs). Statement 3 is correct: G-Secs are issued through auctions conducted by RBI. Auctions are conducted on the electronic platform called the E-Kuber, the Core Banking Solution (CBS) platform of RBI.
'B' is 37.5% more productive than 'A'. Together, they can finish a task in 40 days. How many days would it take for 'A' alone to complete the entire task?
'Asmita,' who is three times as efficient as 'Bittu,' can complete a task on her own in 15 days. 'Asmita' and 'Bittu' began working together, but after ...
A2 type ‘P’ pipes can fill a tank in 450 hours, while B2 type ‘Q’ pipes can fill the same tank in 6...
12 men take 6 days to complete a piece of work. They worked for a period of 2 days. After that, they were joined by 4 more men. How many more days will ...
‘n’ men working 16 hours a day can complete a work in 10 days while (2n – 4) men working 10 hours a day can complete the same work in ...
The efficiency of A is half than that of B and C together. The ratio of the efficiency of B and C is 5 : 4. A, B and C together can do this work in 12 d...
Pipes ‘A’ and ‘B’ can fill a tank in 9 hours and 12 hours, respectively. If pipe ‘C’ is opened along with pipes ‘A’ and ‘B’, then th...
Billy, Tony and Mike were three workers, employed by a Contractor. They completed the whole work in 20 days. Initially all of them worked together, but ...
Working individually, 'A' can finish 60% of a task in 18 days, and 'B' takes 15 days longer than 'A' to complete the entire task. However, 'B' and 'C' w...
5 Pandavas can do a work in 18 days, 4 Kauravas can do the same work in 30 days. Now, in how many total days the total work be finished if 1 Panadva and...