πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    Question

    If 36 persons can finish 50% of work in 12 days In how

    many days 72 person can finish the complete work?
    A 6 Correct Answer Incorrect Answer
    B 3 Correct Answer Incorrect Answer
    C 9 Correct Answer Incorrect Answer
    D 12 Correct Answer Incorrect Answer

    Solution

    let the total work =1 M1 D1 H1/W1 = M2 D2 H2/W2 36Γ—12 /(1/2) =72Γ—D2 /1 D2 =12days.

    Practice Next

    Relevant for Exams:

    ask-question