Question
If 36 persons can finish 50% of work in 12 days In how many days 72 person can finish the complete work?
More CSAT GS Questions
- The greatest advantage of human beings having two eyes is
- Penicillium is a _____________.
- If the volume of a cube is 27cm³, then the diagonal of cube is
- Two dice are thrown and the sum of the number is noted. The number of ways in which the sum can be 7 is
- A, B, C, D and E are standing in row. 'A' is between 'B' and 'D'. E is not at the starting of row. 'C' is just before D. Study above statement and answer t...
- 40% of an amount is Rs 55. 160% of the same amount will be
- The headquarter of RBI is situated at-
- The Tirathgarh waterfall is found in the state of
- Pointing a man in a photograph, Karina Said, "His mother is the only daughter of my mother, How is Karina related to the man of photograph.
- Question 10
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)