Time taken by B to complete the work = 16 days Time taken by C to complete the work = 16/2 = 8 days Time taken by A to complete the work alone = 8 + 4 = 12 days Work done by A, B and C together in 1 day. ⇒ (1/16 + 1/8 + 1/12) = (3 + 6 + 4)/48 = 13/48 this means if would take 48/13 days for A, B and C to complete the work together ∴ Time taken A, B and C to complete 13 works = 13 × 48/13 days = 48 days
In each of the following giving number series, a wrong number is given. Find out the wrong number?
46 23 23 34.5 70 172.5
...21, 32, 45, 60, 75, 96
532, 276, 144, 84, 52, 36
9 17 53 103 310 619
...24, 12, 22.5, 45, 157.5, 708.75
45, 54, 72, 95, 131, 180
8 12 21 36 62 98
98, 128, 162, 200, 244, 288
324, 314, 294, 264, 224, 184
640 1920 240 720 92 270