Question

    A work can be completed by ‘A’ and ‘B’, alone in 15 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if ‘A’, ‘B’ and ‘C’ together can complete the whole work in 4 days.

    A 10 days Correct Answer Incorrect Answer
    B 10.5 days Correct Answer Incorrect Answer
    C 12.5 days Correct Answer Incorrect Answer
    D 12 days Correct Answer Incorrect Answer

    Solution

    Let total work = 30 units (LCM of 15 and 10) Efficiency of ‘A’ = (30/15) = 2 units/day Efficiency of ‘B’ = (30/10) = 3 units/day Combined efficiency of ‘A’, ‘B’ and ‘C’ = (30/4) = 7.5 units/day Efficiency of ‘C’ = 7.5 – (2 + 3) = 2.5 units/day Required time taken = (30/2.5) = 12 days

    Practice Next

    Relevant for Exams:

    ×
    ×