A work can be completed by ‘A’ and ‘B’, alone in
15 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if ‘A’, ‘B’ and ‘C’ together can complete the whole work in 4 days.Solution
Let total work = 30 units (LCM of 15 and 10) Efficiency of ‘A’ = (30/15) = 2 units/day Efficiency of ‘B’ = (30/10) = 3 units/day Combined efficiency of ‘A’, ‘B’ and ‘C’ = (30/4) = 7.5 units/day Efficiency of ‘C’ = 7.5 – (2 + 3) = 2.5 units/day Required time taken = (30/2.5) = 12 days
What is the target year for Swachh Bharat Mission-Urban 2.0?
What is the objective of PM krishi sinchayee Yojana, which was launched in 2015-16.
(i)Â Â Â Â Â Â Â Â Â Â To achieve convergence of investmen...
Which of the following States does not have any PVTGs?
Union Minister of Cooperation Amit Shah e-launched the onboarding of cooperatives on the Government e-Marketplace (GeM) portal in New Delhi, Delhi. The ...
The Election Commission of India has celebrated _______ National Voters’ Day on 25th January 2024.
Jal Jivan Mission started in the year 2019-20 and targeted with providing tap water connection by the year____?
Which section of the Companies Act 2013 deals with Independent Directors?
What is the primary objective of the Smart Cities Mission in India?
Consider the following statements about the National Skill Development Corporation (NSDC) under the Skill India Programme:
1.        NS...
In the Budget 2022-23, how much has been allocated for promoting scientific organic farming in north-east states?