Question

    A buffalo alone can plough field ‘A’ in 10 days. A

    Bull alone can plough the field ‘A’ in 15 days. Find the number of days taken by 3 bulls and 2 buffalo to together plough field ‘B’ that is 20% larger than field ‘A’?
    A 2 days Correct Answer Incorrect Answer
    B 5 days Correct Answer Incorrect Answer
    C 3 days Correct Answer Incorrect Answer
    D 4 days Correct Answer Incorrect Answer

    Solution

    Let the total work done to plough field ‘A’ = 30 units (LCM of 10 and 15) Then, efficiency of a buffalo = (30/10) = 3 units/day Efficiency of a bull = (30/15) = 2 units/day Total work required to plough field ‘B’ = 30 × 1.20 = 36 units Combined efficiency of 3 bulls and 2 buffalo = 2 × 3 + 3 × 2 = 12 units So, number of days required to plough field ‘B’ = 36/12 = 3 days

    Practice Next

    Relevant for Exams: