Question

    Ashish and Anil can do a piece of work in 14 days and 20 days respectively. Ashish completed 45% of the work. Find the time taken by Anil to complete the remaining work.

    A 15 days Correct Answer Incorrect Answer
    B 13 days Correct Answer Incorrect Answer
    C 11 days Correct Answer Incorrect Answer
    D 10 days Correct Answer Incorrect Answer

    Solution

    Let the total work be (LCM of 14 and 20) = 140 units Efficiency of Anil = 140/20 = 7 units/day Remaining work = 140 x 0.55 = 77 units Time taken by Anil to complete the remaining work = 77/7 = 11 days

    Practice Next

    Relevant for Exams:

    ×
    ×