Question
Every factory is required to be registered with the
______.Solution
Chief Inspector of Factories is responsible for such activity.
- Ajay alone can complete a work in 50 days. Vijay is four times as efficient as Ajay. Find the percentage of work completed by Ajay and Vijay together in 10...
Numan does 4/ 5 half the work as Gagan in time. If together they take 16 days to complete a piece of work, then how long will Gagan take to complete the...
βmβ painters can paint a house in 60 days. If the crew increased by 25 painters, they could finish in 40 days. What is the value of βmβ?
...P and Q together can do a job in 6 days, Q & R can finish the same work in 60/7 days. P started the work and worked for 3 days. Q & R continued ...
A can finish a task by himself in 25 days, whereas B can finish the same task by himself in 10 days. A begins the task but stops after 5 days, at which ...
A and B together can complete a piece of work in 12 days, while B and C can complete it in 15 days. A, B, and C together can complete the same work in 8...
- 'Rahul', 'Amit', and 'Vikram' together can complete a work in 20 days. 'Rahul' and 'Amit' together can complete the same work in 60 days. 'Vikram' alone ca...
X can do a piece of work in 20 days. He worked at it for 5 days and then Y finished it in 15 days. In how many days can X and Y together finish the work?
Neha and Priya are assigned a piece of work. Neha can complete 8 units of work each day, while Priya can finish the whole task alone in 32 days. If the ...
Ishan alone can do a certain piece of work in 'w' days and Bhanumati can do it in '2w' days (w is a positive integer). Both together can do the work in ...