Which of the following schedule is responsible for the listing about the public utility services under the Industrial Dispute Act 1947?
The First Schedule of the Industrial Disputes Act, 1947, provides a list of industries that are deemed to be public utility services. These industries are considered essential for the public interest and are subject to certain regulations and provisions under the Act.
P and Q together can do a job in 6 days, Q & R can finish the same work in 60/7 days. P started the work and worked for 3 days. Q & R continued ...
Ram can produce 5 pots in a day. Rahul is 40% faster than Ram in pot-making. Together, they work for a period of 55 days, resulting in the production of...
P alone can finish a piece of work ‘M’ in 5 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ wh...
Ashish and Anil can do a piece of work in 10 days and 18 days respectively. Ashish completed 75% of the work. Find the time taken by Anil to complete th...
A can complete a piece of work in 27 days. He worked for 21 days and then B finished the remaining work in 8 days. In how many days can A and B finish t...
The ratio of time taken by P, Q and R to complete work alone is 6:8:3 respectively. If all three together complete the work in 5 days, then find in how ...
If 24 persons can finish 50% of work in 12 days in how many days 48 person can finish the complete work?
Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed ...
Working alone, ‘X’ and ‘Y’ can complete a work in 16 days and 10 days, respectively. They started working together but af...
35 typists working 9 hours per day can complete a typing job in 14 days. ____ typists working _____ hours per day can complete (3/4)th part of the work ...