The correct answer is C
A can complete a work in 10 days. B takes 4 days less than A to complete the same work. In how many days can both of them together complete 80% of the w...
Carol, Bruce, and Peter can decorate a venue in 7, 14, and 21 days respectively. If they start working together, but Carol leaves 3 days before completi...
Ajay and Bheem collectively earned Rs.9,000 for completing a task, with Bheem's share being Rs.3,000. If Bheem can complete the work on his own in 48 da...
25 men and 45 women can complete a piece of work in 15 days, while 15 men and 60 women can complete it in 20 days. In how many days can 69 men and 67 wo...
28 typists working 5 hours per day can complete a typing job in 18 days. ____ typists working _____ hours per day can complete (5/6)th part of the work ...
Person A can complete a work in 90 minutes while Person B takes 54 minutes to complete the same work. How much time will both take together to complete ...
7 men and 4 boys can complete a work in 6 days. A man completes double the work than a boy. In how many days will 5 men and 4 boys complete the work?
A can complete a work in 15 days. B takes 6 days less than A to complete the same work. In how many days can both of them together complete 80% of the w...
A group of 24 men is capable of finishing a task in 15 days. Initially, 12 men begin the job and work on it for 12 days. After this period, an additiona...
A and B together can complete a piece of work in 25 days while A alone can complete 50% of the work in 50 days. Find the time taken by B to compl...