A group of workers was put on a job. From the second day onwards, 1 worker left work everyday. If no worker was left when 52% of the work gets complete...
A can do a piece of work in 40 days. A is 25% more eicient than B. In how many days the work gets completed when both of them work together?
Pawan can finish a task in 28 days, while Bhavna requires 7 more days than Pawan to complete the same task. They both started wor...
A and B together, B and C together and A and C together can complete a piece of work in 14 days, 15 days and 18 days respectively. Find the ratio of the...
If 16 men working 16 hours a day can make 16 quilts in 16 days, then in how many days 32 men working 32 hours per day will make 32 quilts?
Anupam requires 30% more time than Aman to complete a certain task. If both of them work together and earn a total of Rs. 23,000, determine Anupam's sha...
Ajay, Bjay, and Cheetna can individually finish a task in 20, 24, and 30 days, respectively. They began working together, but Ajay left the task 10 days...
P and Q can do a piece of work in 32 and 40 days respectively. They began to work together but P leaves after sometimes and Q completed remaining work i...
P can construct a robot individually in 20 hours, while Q requires 40 hours to complete the same task. If they collaborate, how many hours will it take ...