The correct answer is B
A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alon...
33 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for ...
P, Q, and R can complete a work in 12 days. 15 days and 30 days, respectively, working alone. How soon can the work be completed if Q is assisted by P a...
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alo...
18 skilled workers can complete a task in 12 days while 24 semi-skilled workers need 15 days to complete the same task. 12 skilled workers started the t...
A alone work for 6 days then left the work and B alone finishes remaining work in 12 days. If ratio of time taken by A alone to B alone to finish work ...
A can finish a work in 25 days and B can complete the same work in 10 days. B worked for 5 days and left the job. In how many days can A alone finish th...
A and B can jointly finish a task in 42 days, while B and C together take 35 days to finish the same task. If B can finish the task alone in 105 days, h...
Asmita and Bhanu working together can complete the task in ____ days, and the efficiency of Sam is 50% more than that of Asmita. Bhanu alone can complet...
P can complete a piece of work in 15 days. Q in 20 days and R in 30 days. P and R worked together for three days and then P was replaced by Q. In how ma...