Question

    Which of the following statement is/are INCORRECT

    regarding Green Energy Corridor (GEC) Phase-II-Inter-State Transmission System (ISTS) for 13 GW Renewable Energy Project in Ladakh? 1. This project was approved On 18 October 2023. 2. The Cabinet Committee on Economic Affairs, chaired by the Hon'ble Prime Minister, Shri Narendra Modi approved this project. 3. The project is targeted to be set up by FY 2029-30 with total estimated cost of Rs.20,773.70 crore 4. The project will contribute to achieving the target of 500 GW of installed electricity capacity from non-fossil fuels by year 2050
    A 1 and 2 only Correct Answer Incorrect Answer
    B 4 only Correct Answer Incorrect Answer
    C 2 only Correct Answer Incorrect Answer
    D 2 and 3 only Correct Answer Incorrect Answer

    Solution

    The correct answer is B

    Practice Next

    Relevant for Exams: