Question
15 male employees or 20 female employees of a company
can complete a project in 26 days. How long will 30 male employees and 12 female employees together take to complete the project?Solution
15 males × 26 days = 20 females × 26 days ∵ 15 males = 20 females ∴ 30 males = 40 females Total work in terms of females = 20 females × 26 days = 520 units No of days taken by 30 males and 12 females: ⇒ (40 females + 12 females) = 52 females ∴ No of days taken = 520 units /52 females = 10 days
Who has been named as India’s flag bearer for the Closing Ceremony of the Paris 2024 Olympics, following her outstanding performance at the games?
Who is the first Agniveer to be martyred in the line of duty at the Siachen glacier, the world's highest battlefield, since the introduction of the Agni...
According to the “State of Healthcare in Rural India, 2024” report, what percentage of rural households have access to subsidized medicines through ...
In the Under-19 Asia Cup 2021 finals India defeated which country by 9 wickets in a rain-interrupted One-Day International final in Dubai.
Which initiative has Microsoft integrated into its products to enhance productivity?
Which relaxation did the RBI provide in qualifying asset criteria for NBFC-MFIs?
By how much did India’s Maternal Mortality Ratio (MMR) fall between 2014 and 2021?
Which of the following public sector oil company had launched HaPpy Shop store for costumers in affordable prize for home utility products including foo...
What grid resolution is used by India’s Bharat Forecast System (BFS) for weather prediction?
NPCI has extended UPI volume cap deadline till _______.