The correct answer is D
Ram, Ankit and Shivam together can do a piece of work in 10/3 days. Ram could do it alone in 6 days and Ankit could do it alone in 12days. In how many d...
A’ and ‘B’ alone can do a certain work in 20 days and 30 days, respectively. Both started the work together but after ‘x’ days ‘A’ left th...
‘A’ and ‘B’ can complete a certain work in 12 days and 24 days, respectively. They started working together and worked till completion of the wo...
‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 12 days. If they work together for the entire time and get paid Rs.120...
A contractor hired 40 workers to complete a work in 100 days. After 70 days, it was found that only 2/5th of the work was completed. Find the number of ...
If 18 men working 18 hours a day can make 18 quilts in 18 days, then in how many days 27 men working 12 hours per day will make 27 quilts?
‘P’ and ‘Q’ can complete a project in 45 days and 60 days respectively while ‘P’, ‘Q’ and ‘R’ together can complete the same project...
Akhil and Nikhil together can complete a work in 10 days while Nikhil alone takes 20 days to complete 40% of the work. If the efficiency of Sachin is 25...
A can complete a piece of work in 27 days. He worked for 21 days and then B finished the remaining work in 8 days. In how many days can A and B finish t...
A can do a piece of work in 21 days and B in 28 days. If they together work on it for 5 days, then the fraction of the work that is left is :