Question
Based on the data of the year 2021-22, what was the
contribution of the primary sector in the state's economy?Solution
Contribution of three sectors of the economy at current prices (in percentage) for the year 2021-22 1. Primary- 12.36% 2. Secondary, 46.21 3. Tertiary- 41.43
Ravi and Sita together can complete a piece of work in 150 days and 3 minutes, while Sita and Ramesh together can complete the same work in 90 days and ...
V and N, working individually, can complete a task in (w β 2) days and (w + 4) days, respectively. N initiated the task alone and was later joined by ...
25 men and 45 women can complete a piece of work in 15 days, while 15 men and 60 women can complete it in 20 days. In how many days can 69 men and 67 wo...
βAβ alone can complete a work in 50 hours. βAβ started the work alone and left after working on it for 30 hours. If βBβ completed the rest o...
A and B together can complete a piece of work in 12 days. B and C together can complete the same work in 15 days, and A and C together can complete it i...
132 unit of work can be completed by P alone in 22 days. P started working alone and joined by Q after 10 days such that they completed the remaining wo...
Four boys and nine girls can complete a task in 24 days. Three boys and five girls can finish the same task in 36 days. How many ...
Armaan and Bhanu working together can finish a certain task in 90 days, and Bhanu collaborating with Chintu can complete the same task in 70 days. If Ar...
βPβ alone can do 60% of a work in 18 days and βQβ alone can do 30% of the same work in 9 days. βPβ, βQβ and βRβ together can finish ...
Person A can complete a work in 90 minutes while Person B takes 54 minutes to complete the same work. How much time will both take together to complete ...