    COCOMO is a model used for

    estimating:
    A Project schedule Correct Answer Incorrect Answer
    B Project cost Correct Answer Incorrect Answer
    C Project risks Correct Answer Incorrect Answer
    D Project quality Correct Answer Incorrect Answer

    Solution

    Project cost