Question

    Which COCOMO mode provides a more detailed estimation based on individual project characteristics?

    A COCOMO 81 Correct Answer Incorrect Answer
    B COCOMO II Correct Answer Incorrect Answer
    C COCOMO 2.0 Correct Answer Incorrect Answer
    D COCOMO Basic Correct Answer Incorrect Answer

    Solution

    COCOMO II

    Practice Next

    Relevant for Exams: