A alone can do a piece work in 15 days and the time taken by A alone is 50% more than the time taken by B. They started work together alternatively star...
βXβ can complete a job in 30 days. βYβ is 50% more efficient than βXβ. How long will they take to finish 75% of the work together?
...Vijay can do a piece of work in 32 days and Sanjay can do the same work in 48 days. If Vijay works for 2 days and got Rs. 960, and the remaining work wi...
A can fabricate a divider in 10 days , while B alone can assemble it in 30 days, If they construct it together and get an installment of Rs 8200, then f...
βAβ and βBβ alone can do a certain work in 30 days and 40 days, respectively. Both started the work together but after βxβ days βAβ left...
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days w...
P alone can finish a piece of work βMβ in 8 days while Q takes 4 days to finish it alone. P, Q and R working together can finish the work βNβ wh...
βAβ and βBβ can do a piece of work in 20 days and 30 days, respectively. If they started the work together and worked on it for 7 days, then fin...
A, B, and C are hired to complete a task. A and B together can finish the work in 12 days, B and C together in 15 days, and A and C together in 20 days....
- Person 'X' can finish a task in 40 days while 'Y' can do it in 50 days. How long will it take if both work together?