If 24 persons can finish 50% of work in 12 days in how many days 48 person can finish the complete work?
Calculate the number of days it would take for a team of 8 boys, 5 girls, and 5 children to Construct a building. This building was previously constru...
Consider that 'A' and 'B' were collectively paid Rs. 9,000 for a job. Out of this amount, 'B' received Rs. 3,000. If 'B' can finish this task solo in 48...
A and B together can complete a work in 20 days. After working together for 8 days, B leaves, and A completes the remaining work in 16 more days. In how...
A can complete a piece of work in 27 days. He worked for 21 days and then B finished the remaining work in 8 days. In how many days can A and B finish t...
‘A’ can do a piece of work in 8 days. ‘B’ can do 40% of the same work in 16 days. If they work together for the entire time and get paid Rs.1500...
A team leader can do a job as fast as three members of the team working together. If one of the member can do the job in 5 hrs, the second one takes 10 ...
A can complete 5/6 of a work in 15 days and B can complete 2/3 of work in 8 days. In how many days both A and B together can complete the work?
'Akshay' alone can do a piece of work in 25 days. 'Ben' alone takes 40 days to do the same work. How much 'Akshay' should be paid out of total wages of ...