Question
28 men and 21 women can complete a work in 16 days. All of them start working together and after working for 12 days the women stopped working. All men alone complete the remaining work in 8 days. How many days will it take for completing the entire work if only 21 women are employed on the job?
More Approximation Questions
- What approximate value should come in place of question mark in the following question? (39.9 × 4.1 + 59.8 × 5.9) ÷ 9.9 = ?
- 40.05% of 210.05 – 10.15% of 109.99 × 5.02 = ?
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.) ...
- 960.11 ÷ 23.98 × 5.14 – 177.9 = √?
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exactvalue.) ...
- ?% of 399.99 + 139.99 ÷ 6.99 = 59.99% of 559.99 + 41.09 X 15.99
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.) (...
- {44.78% of (11.67 × 54.78)} ÷ 2.65 = ? + 19.25
- 32.12% of 2399.98 + 64.04% of 2499.95 = ? × 15.95
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.) (...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)