Question
An intern was paid a stipend of Rs. 1,792 for a period
of 30 days calculated on daily basis. During this period, he was absent for 4 days and was fined Rs. 12 per day for absence. He was given full amount for only 20 days as he was late for the rest of the days and he got only half of the amount on the late days. Had the intern come on time every day, not being absent on any day, what stipend he would have been received?Solution
Let the stipend per day of the intern be Rs. x He came late for 30-(20 +4) = 6 days Then, 20x [if gte msEquation 12]>
Ankit began a task but left it after working for 32 days. The remaining 60% of the task was then completed by Bittu and Sittu wor...
P and Q together can do a piece of work in 30 days, Q and R together can do it in 20 days. P starts the work and works on it for 5 days, then Q takes it...
A is twice efficient as B and B can do a piece of work in 40 days. B started the work and after a few days A joined him. They completed the work in 32 ...
8 children and 6 women together can complete a piece of work in 10 days and work done by a children in one day is one-third of the work done by a women ...
Aman, Bishnu, and Chintu can each complete 20%, 25%, and 60% of the work in 4 days, 9 days, and 27 days, respectively. If all thr...
An elephant can do a work as fast as two horses βAβ and βBβ can do it by working together. If horse βAβ alone can complete the work in 38 ho...
Some Category of workers can complete a decided project in 20 days. However, due to some unpredicted situation, 5 workers were absent. Thatβs why, the...
A contractor undertook to make 20 km of roadway in 48 weeks. In 28 weeks, 8 km was completed by 120 men working 12 hours a day. The men then agreed to w...
X can do a piece of work in 22 days. He worked at it for 11 days and then Y finished it in 15 days. In how many days can X and Y together finish the work?
12 man can make a wall in 6 days. How many men required to complete the same work in 3 days ?