Question
Number of males of tribe Raba is what percentage more
than the number of males of tribe Dimasa? Answer the following questions based on the information given below: There are two tribes (Raba and Dimasa) in Mizoram. Total population of tribe Raba is 4800. Number of males of tribe Raba is 40% more than the number of females of tribe Raba. Total population of tribe Dimasa is 20% more than the population of tribe Raba. Ratio of number of males to the number of females of tribe Dimasa is 5:7.Solution
Let the number of females of tribe Raba be x. Number of males of tribe Raba = 1.4x Total population = 4800 => x + 1.4x = 4800 => x = 2000 Number of males of tribe Raba = 1.4 × 2000 = 2800 Number of females of tribe Raba = 2000 Total population of tribe Dimasa = 4800 × 1.2 = 5760 Number of males of tribe Dimasa = (5/12) × 5760 = 2400 Number of females of tribe Dimasa = (7/12) × 5760 = 3360 Required % = [(2800 – 2400)/2400] × 100 = 16.67%
A and B individually can complete the work in 30 days and 45 days respectively. If the time taken by C alone to complete the work is 1.5 times the time ...
P can do a piece of work in 15 days, Q can complete double the work in 60 days and R can do the work in 40 days. If all of them together earn Rs. 3000, ...
A and B can complete a task together in 14 days, while B alone takes 28 days to finish it. A began working alone and left after βxβ days, after whic...
A can do a piece of work in 15 days, B is 25% more efficient than A, and C is 40% more efficient than B. A and C work together for 3 days and then C lea...
Ram can do a work in 60 days while Mohan can do the same in 84 days. If Ram work for 'x' days while Mohan work for ' x + 2' days then one-third of the w...
- X and Y can complete a task together in 24 days, while Y alone takes 48 days to finish it. X worked alone for some days and then Y completed the rest of th...
- Two pipes, P and Q, can fill a tank in 60 minutes and 100 minutes, respectively. A third pipe R can empty it in 1 hour 40 minutes. Initially, pipes P and R...
35 men can complete a piece of work in 40 days. βxβ men started the work and after 30 days 60 more men joined them so that whole work was finished i...
Thirty men working 8 hours daily complete a task in 16 days. If the work increases to three times the original and needs to be fi...
βMβ is 60% more efficient than βNβ. βNβ started the work alone and worked for 20 days and after that βNβ is replaced by βMβ. If the ...