Question
There are a total of 55 bats
(cricket bats + baseball bats) in two bags, 'P' and 'Q.' Bag 'P' contains 12 cricket bats and 'x' baseball bats, while bag 'Q' contains 'y' cricket bats and 10 baseball bats. What is the difference in the number of bats between the two bags? Statement I: After transferring 3 cricket bats from bag 'Q' to bag 'P,' the probability of picking a cricket bat from bag 'P' becomes (1/2). Statement II: If all Baseball bats from bag 'P' are moved to bag 'Q,' the number of Baseball bats in bag 'Q' will be 7 more than the number of cricket bats in that bag. The following question has two statements labeled "I and II." Based on the provided information, determine if the statements are sufficient to answer the question.Solution
ATQ, We have, 12 + x + y + 10 = 55 Or, x + y = 55 - 22 = 33 --------- (I) Statement I: Number of cricket bats in bag 'P' now = 12 + 3 = 15 Probability of drawing a cricket bats from bag 'P' now = 15 Γ· (15 + x) So, 15 Γ· (15 + x) = (1/2) Or, 30 = 15 + x Or, 'x' = 15 On putting value of 'x' in equation (I) , We get, 15 + y = 33 Or, 'y' = 18 So, number of bats in bag 'P' = 12 + x = 12 + 15 = 27 Also, number of bats in bag 'Q' = y + 10 = 18 + 10 = 28 Required difference = 28 - 27 = 1 So, data in statement I alone is sufficient to answer the question. Statement II: Number of Baseball bats in bag 'Q' now = (10 + x) So, 10 + x = b + 7 Or, y - x = 3 ..........(III) On adding equations (I) and (III) , we get, 'y' = 18 And, putting value of 'y' in equation (I) , we get, 'x' = 33 - 18 = 15 So, number of bats in bag 'P' = 12 + a = 12 + 15 = 27 Also, number of bats in bag 'Q' = b + 10 = 18 + 10 = 28 Required difference = 28 - 27 = 1 So, data in statement II alone is sufficient to answer the question. Therefore data either in statement I alone or in statement II alone is sufficient to answer the question
'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 18 days. 'A' started the work alone and worked...
A takes 32 days to complete a work while B can complete the same work in 12 days less than A. If C can complete 25% of the work in 12 days, then find th...
- Alok finishes 60% of a project in 30 days, while Neha finishes 20% of the same in 15 days. Alok worked for 25 days and then stopped. Find the time taken by...
A and B individually can complete the work in 32 days and 48 days respectively. If the time taken by C alone to complete the work is 1.25 times the time...
Efficiency of a man is 25% more than that of a woman. (2n + 4) men working 8 hours a day can complete a task in 18 days, whereas (3n - 2) women working...
120 unit of work can be completed by P alone in 20 days. P started working alone and joined by Q after 10 days such that they completed the remaining wo...
If 15 men or 10 boys can finish a task in 18 days, how long will it take for a team of 12 men and 15 boys to complete the same task? (Calculate approxim...
A and B can do a piece of work in 15 and 20 days respectively. They work together for 5 days, then A leaves. How long will B take to finish?
- Pipes X and Y can fill a tank in 48 minutes and 80 minutes respectively. Another pipe Z can empty the tank in 2 hours. X and Z are opened together. If afte...
28 men can complete a piece of work in 12 days. 12 men started the same work and worked for 10 days, and then joined by βxβ more men such that the r...