Question
Two contractors, X and Y, are assigned to finish a
construction project that consists of three phases. Each contractor works at a constant rate for each phase. What is the total number of hours taken by Contractor X to complete all three phases? Statements: 1. The total hours worked by Contractor Y on all three phases is 80% of the total hours worked by Contractor X. Contractor Y worked for 200 hours in the first phase, 300 hours in the second phase, and 250 hours in the third phase. 2. Contractor X spent twice as much time on the first phase as Contractor Y. Contractor X's time spent on the second phase is 150% of the time spent on the first phase.Solution
From Statement 1: Contractor Y’s total time is 200 + 300 + 250 = 750 hours. This is 80% of the time taken by Contractor X, so Contractor X’s total time is 750 / 0.8 = 937.5 hours. this alone is sufficient. From Statement 2: Contractor X’s time in the first phase is twice Contractor Y’s, So without help of statement 1 answer can’t be calculated. Statement 2 alone is not sufficient. Correct Answer: (a) Statement 1 alone is sufficient, but statement 2 alone is not sufficient.
Aarif, Arun, and Abraham can do work in 12, 15, and 24 days, respectively. They all begin together. Aarif leaves the work 1 day, Arun 3 days and Abraham...
‘A’ can do a piece of work in 10 days. ‘B’ can do 70% of the same work in 20 days. If they work together for the entire time and get paid Rs.108...
A' can finish a job in 24 days, while 'B' is 25% less efficient than 'A.' If they take turns working, beginning with 'A,' how many days will it take for...
A 40 hectare field is reaped by 4 men, 6 women and 8 children together in 10 days. If working capabilities of a Man, a Woman and a Child are in the rati...
P and Q agreed to complete a task for Rs. 6600. P can finish the work alone in 12 days, and Q can complete it alone in 10 days. I...
Pawan completes in two days the same amount of work that Qureshi completes in four days. Pawan alone can finish the entire task in 15 days. How many day...
A group of 24 men is capable of finishing a task in 15 days. Initially, 12 men begin the job and work on it for 12 days. After this period, an additiona...
A can complete 25% of work in five days. And this takes four days more than B to complete the whole work. They started the work together but after X day...
'Q' is 20% less efficient than 'P' and 'R' is 60% more efficient than 'P'. If 'Q' takes 20 more days than 'R' to complete the same work, then find the t...
A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work on alternate days. In how many days, total work will be comple...