Question
How much profit did the company earn in the year
2016? I) The company earned 45% more profit in the year 2017 than that in the year 2015. II) The company earned a total profit of Rs. 25 crores in the year 2015 and 2016 taken together. III) In the year 2017, the company earned 75 percent profit of that in 2016. In each of the following questions, a question and three statements I, II and III are given. You have to decide whether the date given in the statements are sufficient to answer the question or not.Solution
Taking all statements together, Let the profit earned by company in 2015 = Rs.x and in 2016 = Rs.y Profit earned in 2017 = 1.45x ,x+y = Rs. 25 crore ...... (i) From statement III, 1.45x = y x 75/100 y = 3/4 x 1/1.45y = 30/58y ......(ii) From equations (i) and (ii), we can get the required profit.
A, B, and C are hired to complete a task. A and B together can finish the work in 12 days, B and C together in 15 days, and A and C together in 20 days....
'A' and 'B' alone can complete a work in 9 days and 18 days, respectively. Find the time taken by them to complete the work if they work on alternate da...
- Neha and Seema can finish a work in 10 days and 25 days, respectively, when working alone. Neha started the work. After how many days should Seema join to ...
A is five times as efficient as B and can finish a piece of work in 24 days less than B. B can finish this work in how many days?
A and B can complete a task together in 26 days, while B alone takes 52 days to finish it. A began working alone and left after ‘x’ days, after whic...
Arjun can finish 60% of a job in 9 days. Bittu needs 9 more days than Arjun to finish the whole job, and Bittu’s efficiency is 25% higher than Charu�...
‘A’ alone can do some work in 13 days. ‘B’ and ‘C’ together can do the same work in 18 days. If ‘B’ is half as efficient as ‘A’, the...
Akhil and Nikhil together can complete a work in 5 days while Nikhil alone takes 10 days to complete 40% of the work. If the efficiency of Sachin is 25%...
Sam alone can complete a work in 60 days. Arun is three times as efficient as Sam. Find the percentage of work completed by Sam and Arun together in 15 ...
Working alone, B can complete the work in 25 days. C is twice as efficient as B and A takes 2.5 days more than it takes C to complete the work. Working ...