Question
The number of chocolates distributed in class V is
approximately what percentage more/less than the number of chocolates distributed in class III and VI together? Study the following line chart carefully and answer the questions given below: The following pie chart shows the percentage distribution of chocolates to the students studying in five different classes (i.e. II, III, IV, V and VI) Total number of chocolates = 2500Solution
Number of chocolates distributed in class V = (32/100) × 2500 = 800 Number of chocolates distributed in class III and VI together = (25 + 10)% of 2500 = 875 Required difference = [(875 – 800)/875] × 100 = 9% less (approx.)
Efficiency of a man is 25% more than that of a woman. (n - 10) men working 6 hours a day can complete a task in 18 days, whereas (n - 9) women working ...
'Amit' can finish a __ percentage of work in 4 days on his own. 'Bishnu' requires 4 days less than 'Amit' to complete the same task individually. Conseq...
1 man and 4 women can complete a work in 65 /4 days, while 3 men and 4 women can complete it in 13 /2 days. In whom many days will be 13 women complete ...
βXβ and βYβ together can complete a work in 10 days, while βYβ and βZβ together can complete the work in 8 days. If βYβ takes 12 day...
50 men can complete a piece of work in 15 days. 10 men started the same work and worked for 10 days, and then joined by βxβ more men such that the r...
- 45 engineers working 5 hours a day take 15 days to complete a project. How many engineers working for 4 hours a day are needed to complete three times the ...
P can do a piece of work in 10 days, Q can complete double the work in 30 days and R can do the work in 20 days. If all of them together earn Rs. 3900, ...
John does ½ piece of work in 3 hours, Joe does ¼ of the remaining work in 1 hour and George finishes remaining work in 5 hours. How long w...
- If βXβ finishes a project in 24 days whereas βXβ and βYβ working together can finish it in 15 days, then determine the time βYβ alone will ...
'Y' is 36% less efficient compared to 'X'. If 'X' requires 86.4 days to finish a task, determine how many days 'Y' will take to complete the same task.