Question
Find the maximum value of the function g(x) =
4x3 − 24x2 + 48x – 10 on the set T = {x ∈ R ∣ x2 − 14x + 45 ≤ 0} .Solution
Given, S = {x ∈ ℝ /x2 + 45 ≤ 14x} ∴ x2 + 45 ≤ 14x ⇒ x2 - 14x + 45 ≤ 0 ⇒ (x - 5) (x - 9) ≤ 0 ⇒ x ∈ [5, 9] Now, f(x) = 4x3 − 24x2 + 48x – 10 ⇒ f'(x) = 12x2 - 48x + 48 ⇒ f'(x) = 12(x2 - 4x + 4) = 12 [(x2 - 4x + 4) − 1] = 12(x - 2)2 - 12 ∴ f'(x) > 0 ∀ x ∈ [5, 9] ∴ f(x) is strictly increasing in the interval [5, 9] ∴ Maximum value of f(x) when x ∈ [5, 9] is f(9) = 1394
A can complete a work in 15 days. B takes 6 days less than A to complete the same work. In how many days can both of them together complete 80% of the w...
180 unit of work can be completed by P alone in 30 days. P started working alone and joined by Q after 18 days such that they completed the remaining wo...
‘n’ men working 20 hours a day can complete a work in 8 days while (6n – 4) men working 10 hours a day can complete the same work in 8...
Three machines P,Q and R were hired by a company for a month. Machine P runs 18 hours for 15 days, machine Q runs 20 hours for 18 days and machine R run...
A and B can complete a task together in 14 days, while B alone takes 28 days to finish it. A began working alone and left after ‘x’ days, after whic...
5 girls can do a piece of work in 9 days, 4 boys can do the same piece of work in 8 days, 6 men do the same piece of work in 2 days and 4 women can do t...
Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' ...
- If the efficiency ratio of A, B, and C is 7:9:11, and B and C together can finish a task in 10 days, then how much time will A and B need to complete it?
Komal and Seema individually can complete a task in ‘2a’ hours and ‘5a’ hours respectively. If they together can complete half of the work in 5...
A task can be finished by 'P' and 'Q' alone in 10 days and 5 days, respectively. 'P' and 'Q' started the task together and after 3 days, 'P' was replace...