Three pipe P1, P2 and P3 fill the tank in 15 hours, 10 hours and 20 hours respectively. If all the three pipes opened together and pipe P2 & P1 are closed after three hours, then pipe P3 fill the remaining tank. Find the total time to fill whole tank.
Let the capacity of tank L.C.M. (15, 10, 20) = 60 units Efficiency of pipe P1 = 60/15 = 4 units/hour Efficiency of pipe P2 = 60/10 = 6 units/hour Efficiency of pipe P3 = 60/20 = 3 4 units/hour Tank filled by all the three in three hours = 13 × 3 = 39 units Remaining tank filled by pipe P3 = (60−39)/3 = 7 hours Total time = 3 + 7 = 10 hours
P can do a piece of work in 10 days, Q can complete double the work in 20 days and R can do the work in 15 days. If all of them together earn Rs. 3200, ...
A work can be completed by ‘A’ and ‘B’, alone in 14 days and 7 days, respectively. Find the number of days taken by ‘C’ to complete the same...
Find the value of "w" if Armaan can complete a Sales target in (w + 20) days, Malik can complete it in (w + 44) days, and when they work together, they ...
A man’s average income for the first 3 months is 12% of his total income. For the next 6 months the average monthly income was Rs. 25,400. His total i...
Anil and Ashish receive Rs.2000 for work of 8 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
Three machines P,Q and R were hired by a company for a month. Machine P runs 18 hours for 15 days, machine Q runs 20 hours for 18 days and machine R run...
A can do a work in 45 days and the same the work is done in 15 days by A and B together, then in how many days B can complete the 20% of work?
A and B together can complete a piece of work in 55 days while B and C together can complete the same work in 66 days. All of three togeth...
P can do a piece of work in 10 days. Q can do it in 16 days. With the help of R, they finish the work in 4 days. In how many days can R alone do the who...
A can complete `1/4` of a work in 6 days and B can complete `2/5` of the work in 12 days. In how many days can both A and B together complete the work?<...