Question
Two pipes 'P' and 'Q' together can fill a tank in 16
minutes while 'Q' alone can fill the tank in 24 minutes. How much time does pipe 'P' alone need to fill the tank?Solution
Let the total capacity of the tank be 48 litres. {LCM (16 and 24)} So, the efficiency of pipe 'Q' = 48 ÷ 24 = 2 litres/minute Combined efficiency of pipe 'P' and 'Q' = 48 ÷ 16 = 3 litres/minute So, the efficiency of 'P' = 3 - 2 = 1 litre/minute So, the required time = 48 ÷ 1 = 48 minutes
(x) men can do some work in 42 days. If 10 more men added then the work would have been completed in 30 days, then in how many days (x+45) men can do th...
Suraj is one third as good as workman as Pankaj and together they finish a piece of work in 36 days. The number of days taken by Suraj alone to finish t...
A and B working together, can do a piece of work in 4(1/2) hours. B and C working together can do it in 3 hours. C and A working together can do it in 2...
Komal and Seema individually can complete a task in ‘5a’ hours and ‘7a’ hours respectively. If they together can complete (4/5)th of the work in...
Anand and Manav can collaboratively finish a task in {40/3} days, while Anand alone requires 24 days to complete the same task. Given that Prachi's effi...
'Zara' is capable of finishing a specific task in 60 days. On the other hand, 'Armaan' takes 40% more time than 'Zara' to complete the same task, while ...
Two individuals, P and Q, can complete a task in (x + 6) days and (x + 3) days, respectively. Another individual, S, is capable of completing 25% of the...
‘A’ alone can complete a work in 40 days while ‘A’ and ‘B’ together can complete the same work in 30 days. How much ...
‘A’ and ‘B’ can complete a certain work in 10 days and 15 days, respectively. They started working together and worked till completion of the wo...
A can complete a piece of work in 27 days. He worked for 21 days and then B finished the remaining work in 8 days. In how many days can A and B finish t...