Work done by A in 1 hour = 1/12, Work done by B in 1 hour = 1/15 Work done by C in 1 hour (emptying) = -1/10 Net work done in 1 hour = (1/12) + (1/15) - (1/10) Taking LCM of 12, 15, and 10 = 60, Net work = (5/60) + (4/60) - (6/60) = 3/60 = 1/20 The tank will be filled in 20 hours. Correct Option: a) 20 hours