Question

    M can do a piece of work in 20 days. He works at it

    alone for 5 days and N alone finishes the remaining work in 9 days. In how many days, both of them together can complete the work ?
    A 12.5 days Correct Answer Incorrect Answer
    B 10 days Correct Answer Incorrect Answer
    C 8 days Correct Answer Incorrect Answer
    D 7.5 days Correct Answer Incorrect Answer

    Solution

    M finishes the work in 20 days So, work done by M in 1 day = 1/20  Work done by M in 5 days =  1/20 × 5 = 1/4 Remaining work = 1 - (1/4)  = 3/4 So, 3/4 work is done by N in 9 days. If the whole work is done by N, 9 × (4/3) = 12 So, work done by N in 1 day = 1/12 (A + B)'s one day of work = (1/20) + (1/12)  ⇒ (3 + 5)/60 = 8/60   M and N will both finish work in 60/8 = 7.5 days. ∴ M and N will both finish work in 7.5 days.

    Practice Next

    Relevant for Exams: