The ratio between the cost price and selling price of article A is 15:17 respectively.
Let’s assume the cost price and selling price of article A is ‘15z‘ and ‘17z‘ respectively.
If the profit on article A while selling is Rs. 600.
selling price of article A - cost price of article A = profit on article A
17z-15z = 600
2z = 600
z = 300
cost price of article A = 15z
= 15x300
= Rs. 4500
The cost price of article B is Rs. 500 less than the cost price of article A.
cost price of article B = Rs. 4500 - Rs. 500
= Rs. 4000
Article B is marked 45% above its cost price and while selling ‘y’ % discount is given on it.
MRP of Article B = Rs. 4000 of (100+45)%
= Rs. 4000 of 145%
= Rs. 5800
The sum of the MRP of articles A and B is Rs. 11500.
MRP of Article A = Rs. 11500 - Rs. 5800
= Rs. 5700
For getting the required difference, we need the selling price of article B. But as per the given information in the question, we cannot determine the selling price of article B. Hence the answer cannot be determined.
Ram, Ankit and Shivam together can do a piece of work in 10/3 days. Ram could do it alone in 6 days and Ankit could do it alone in 12days. In how many d...
A’ and ‘B’ alone can do a certain work in 20 days and 30 days, respectively. Both started the work together but after ‘x’ days ‘A’ left th...
‘A’ and ‘B’ can complete a certain work in 12 days and 24 days, respectively. They started working together and worked till completion of the wo...
‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 12 days. If they work together for the entire time and get paid Rs.120...
A contractor hired 40 workers to complete a work in 100 days. After 70 days, it was found that only 2/5th of the work was completed. Find the number of ...
If 18 men working 18 hours a day can make 18 quilts in 18 days, then in how many days 27 men working 12 hours per day will make 27 quilts?
‘P’ and ‘Q’ can complete a project in 45 days and 60 days respectively while ‘P’, ‘Q’ and ‘R’ together can complete the same project...
Akhil and Nikhil together can complete a work in 10 days while Nikhil alone takes 20 days to complete 40% of the work. If the efficiency of Sachin is 25...
A can complete a piece of work in 27 days. He worked for 21 days and then B finished the remaining work in 8 days. In how many days can A and B finish t...
A can do a piece of work in 21 days and B in 28 days. If they together work on it for 5 days, then the fraction of the work that is left is :