The ratio between the cost price of article A and B is 9:8 respectively. Let’s assume the cost price of article A and B is 9y and 8y respectively. Each of the articles was marked 40% above its cost price. If the MRP of article A is Rs. 2800 more than the MRP of article B. 9y of (100+40)% = 8y of (100+40)% + 2800 9y of 140% = 8y of 140% + 2800 9y x 1.4 = 8y x 1.4 + 2800 1.4(9y - 8y) = 2800 y x 1.4 = 2800 y = 2000 Sum of the cost price of both of the articles = 9y+8y = 17y = 17x2000 = Rs. 34000
Ashish and Anil can do a piece of work in 12 days and 16 days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete th...
X, Y and Z can do a piece of work in 90 days, 40 days and 120 days respectively. If they all work together alternatively starting with X, Y than Z respe...
Ram can do a piece of work in 50 days. He alone worked at it for 20 days and then Lakshman completed alone the rest work in 30 days. In how many days, t...
If 14 men working 9 hours a day can make 24 quilts in 16 days, then in how many days 20 men working 12 hours per day will make 20 quilts?
20 men can complete a piece of work in 40 days. ‘x’ men started the work and after 35 days 64 more men joined them so that whole work was finished i...
A work can be completed by ‘A’ and ‘B’, alone in 15 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the sam...
P’s 5 days work is equal to Q’s 6 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 80% of ...
A is half as efficient as B. C does half as much work as A and B together. If c alone can do the work in 40 days. Then in how many days will A, B and C ...
‘A’ and ‘B’ together can complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in ...
A can do a work in 12 days and B in 16 days. If they work on it together for 3 days then in how many days the remaining work will be completed by B?