I. (4x-5)3 + 1/(4x-5)3 = 2
II. 2[(y+1/y)2- 2]- 9(y+1/y)= -14
I. (4x-5)3+ 1/(4x-5)3 = 2 Let 4x-5=a a3+ 1/a3 =2 a6+ 1=2a³ a6-2a³+ 1=0 (a3- 1)2= 0 a³=1 a=1 4x-5=1 x= 3/2 II. 2[(y+1/y)2- 2]- 9(y+1/y)= -14 Put (y+1/y)=b 2[b2-2]-9b+14=0 2b2- 4-9b+14=0 2b2-9b+10=0 2b2-5b-4b+10=0 b(2b-5)-2(2b-5)= 0 b=2,5/2 If (y+1/y)= 2 y²+1=2y y²+1-2y=0 (y-1)2= 0 y=1 If, (y+1/y)= 5/2 2y2+2=5y 2y2+2-5y=0 2y2- 4y-y+2=0 2y(y-2)-1(y-2)=0 y=2,1/2 Hence, relationship between x and y cannot be established
The ratio of efficiencies of X and Y for doing a certain work is 5 ∶ 9. Working together, they can complete a work in 15 days. X alone will complete 6...
P and Q can complete a work in 26 days and 39 days, respectively. P, Q and R together can complete the work in 13 days. If R get a total wage of Rs. 585...
'Ajeet' has an efficiency that is 40% lower than 'Chirag's, where as 'Bittu' is 20% more efficient than 'Chirag'. The time difference between 'Bittu' an...
‘A’ and ‘B’ can do a piece of work in 30 days and 40 days, respectively. They started working together but ‘A’ left after 9 days. Find the t...
‘A’ and ‘B’ can do a piece of work in 20 days and 40 days, respectively. If they started the work together and worked on it for 6 days, then fin...
P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ wh...
A contractor hired 80 workers to complete a work in 60 days. After 40 days, it was found that only half of the work was completed. Find the number of ex...
X can do a piece of work in 30 days. He worked at it for 5 days and then Y finished it in 20 days. In how many days can X and Y together finish the work?
8 children and 6 women together can complete a piece of work in 10 days and work done by a children in one day is one-third of the work done by a women ...
Abhay and Bhuvan working together can complete a sales target in 24 days. Bhuvan and Chikku working together can finish the same sales target in 32 days...