Question

    If 15 men can complete a work in 24 days, how many days

    will it take 10 men to complete the same work?
    A 10 days Correct Answer Incorrect Answer
    B 17 days Correct Answer Incorrect Answer
    C 16 days Correct Answer Incorrect Answer
    D 12 days Correct Answer Incorrect Answer

    Solution

    ATQ, 15 men / 24 days = 10 men / x days Solving for x, we get: x = (10 men × 24 days) / 15 men = 16 days

    Practice Next