Question

    A can complete a work in 12 days, while B can complete

    it in 15 days. How many days will they take to finish the work together?
    A 6.67 days Correct Answer Incorrect Answer
    B 7 days Correct Answer Incorrect Answer
    C 8 days Correct Answer Incorrect Answer
    D 9 days Correct Answer Incorrect Answer

    Solution

    Work done by A in one day = 1/12. Work done by B in one day = 1/15. Combined work in one day = (1/12 + 1/15) = (5 + 4) / 60 = 9/60 = 3/20. Time taken to finish the work together = 20/3 days = 6.67 days. Correct option: a) 6.67 days