A can complete a task in 24 days, B can complete the same task in 18 days, and C can complete it in 12 days. A and B work together for 4 days, and then C takes over. How many days will C take to complete the remaining work?
Work done by A and B together in 4 days = 4 × (1/24 + 1/18) = 4 × (7/72) = 28/72 = 7/18. Remaining work = 1 - 7/18 = 11/18. C can complete 1/12 of the work per day. Time taken by C to complete 11/18 of the work = (11/18) / (1/12) = 11/18 × 12 = 22/3 = 7.33 days.
With reference to the election of the President of India, consider the following statements:
1. The value of the vote of each MLA varies from S...
Who recently became the first woman officer in the Indian Air Force to be presented a gallantry award?
As per the Economic Survey 2023-24, what was the growth rate of India's real GDP in FY24 compared to its level in FY20?
Consider the following statements about Ohio-class Submarine:
1. They are Diesel-powered submarines used by the United States Navy.
2. ...
Consider the following statements regarding the AAINA Dashboard for Cities:
1. It aims to create a robust database of the key performance metri...
What was the theme of World Earth Day 2024?
Consider the following pairs about the Indian Constitution?
Which state government has recently launched the ‘Swayam scheme’ to provide interest-free loans to empower its youth?
The Ministry of Rural Development and the Ministry of Agriculture and Farmers’ Welfare jointly launched training of Deendayal Antyodaya Yojana- Nation...
Which country will host the 10-day Malabar exercise this year?