Question
A and B together can finish a task in 12 days. B and C
together can complete the same task in 20 days. A and C together complete 33(1/3) % of the task in 5 days. How many days will C take to complete the entire task on their own?Solution
Let the total work = L.C.M of 12, 20 and 5 = 60 units Then, combined efficiency of 'A' and 'B' = 60 ÷ 12 = 5 units/day Combined efficiency of 'B' and 'C' = 60 ÷ 20 = 3 units/day Since, 33(1/3) % =1/3 So, time taken by 'A' and 'C' together to complete the entire work = 5 ÷ (1/3) = 15 days So, combined efficiency of 'A' and 'C' = 60 ÷ 15 = 4 units/day Twice the efficiency of 'C' = (3 + 4) - 5 = 2 units/day So, efficiency of 'C' = 2 ÷ 2 = 1 unit/day So, time taken by 'C' alone to complete the entire work = 60 ÷ 1 = 60 days
Select the figure from among the given options that can replace the question mark (?) in the following series.
Select the figure from the alternatives which will complete the pattern in given question figure.

Find out the missing figure (?) of the problem from among the given answer figures.
What is water image of given figure?

Select an appropriate figure from the four options that would complete the figure.

Which figure is the correct representation of the movement of food in phloem?
Select the combination of numbers that when placed sequentially in the blanks of the given series will complete the series.
m n _ p _ r s _ n _ p...
