Question
A company produces three types of products: X, Y, and Z.
Initially, the production ratio of X to Y to Z is 5:7:8. The total production of these three products is 10,800 units. After a change in the production plan, the number of units produced for type X is increased by 25%, for type Y it is decreased by 10%, and for type Z it remains the same. What is the total production of these three products after the changes?Solution
Let the initial production of X, Y, and Z be 5k, 7k, and 8k respectively, where k is the common multiple. The total production is 10,800 units, so: 5k + 7k + 8k = 10,800 20k = 10,800 k = 540 Thus, the initial production is: X = 5 * 540 = 2700 units Y = 7 * 540 = 3780 units Z = 8 * 540 = 4320 units After the changes: X’s new production = 2700 * 1.25 = 3375 units Y’s new production = 3780 * 0.90 = 3402 units Z’s production remains unchanged = 4320 units The total production after the changes is: 3375 + 3402 + 4320 = 11,097 units Answer: e) none
P and Q together can complete 75% of a work in 15 days while Q alone takes 40% more time than P and Q together to complete the whole work. Find the time...
 Saurabh can complete a piece of work in 20 days. He worked for 5 days and left. Anirudh completed the remaining work in 12 days. If both had done the ...
Ajay and Vijay together can paint a piece of furniture in 11 days. Vijay and Chirag together, as well as Ajay and Chirag together...
If 15 men or 10 boys can finish a task in 18 days, how long will it take for a team of 12 men and 15 boys to complete the same task? (Calculate approxim...
P and Q agreed to complete a task for Rs. 6600. P can finish the work alone in 12 days, and Q can complete it alone in 10 days. I...
'Akshay' alone takes 18 days to finish a work while 'Bhim' alone takes 24 days to finish the same work. If 'Akshay' and 'Bhim' work on alternate days st...
A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alon...
A and B together can complete a piece of work in 32 days while A alone can complete 40% of the work in 32 days. Find the time taken by B to compl...
‘A’ alone can do some work in 20 days. ‘B’ and ‘C’ together can do the same work in 15 days. If ‘B’ is half as efficient as ‘A’, the...
‘A’ and ‘B’ can complete a certain work in 16 days and 32 days, respectively. They started working together and worked till completion of the wo...