Let the sum be Rs.x. According to question, => 4194.4 = x(1.14)2 – x => 4194.4 = 1.2996x – x => 4194.4 = 0.2996x => x = Rs.14000
Virat can do a piece of work in 20 days and Sachin can do the same work in 30 days. If Virat works for 4 days and got Rs. 2400, and the remaining work w...
A and B working together, can do a piece of work in 4(1/2) hours. B and C working together can do it in 3 hours. C and A working together can do it in 2...
A and B together can complete a work in 7.2 days, while B and C together can complete the same work in 12 days. If A is twice efficient than C, then fin...
Rahul, Sameer, and Dinesh can complete a task in 24 days, 36 days, and 18 days, respectively. They started working together, but ...
Ten women working nine hours a day complete a particular job in 20 days. If an additional 20 women were employed and they all worked 12 hours a day, ho...
A and B individually can complete the work in 32 days and 48 days respectively. If the time taken by C alone to complete the work is 1.25 times the time...
x men can finish a work in y days. 0.9x women can finish 1/3rd of the same work in (y - 8) days. If 0.8x women can complete 1/3rd work in 36 days. Find ...
15 people can paint a house in 5 days using 15 paintbrushes. In how many days can 10 people paint the same house using p paintbrushes?
A and B together, B and C together and A and C together can complete a piece of work in 18 days, 15 days and 10 days respectively. Find the ratio...
20 boys working 9 hours a day can finish a task in 12 days. They all worked together initially, but after 10 days, 5 boys left. H...